We intend to keep everyone informed on our progress and the status for the first
release of the Universal Space Systems Space Adventurer
Assessment/Report (SAAR) via this Web page. If you've visited us before
and want to know where we are in the timeline for the first release, take
a look here first.
|
Month/Activity |
Status |
| January
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "dynamic" Space Tourism topics
- Hire additional research staff
|
On-track to meet
all goals and objectives for this month and end of year. All research
staff hiring complete.
|
| February
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "dynamic" Space Tourism topics
|
On-track to meet
all goals and objectives for this month and end of year.
|
| March
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "dynamic" Space Tourism topics
- Release upgrades
to Universal Space Systems Web site as needed
- Assess first quarter's performance
|
On-track to meet
all goals and objectives for this month and end of year.
|
| April
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "dynamic" Space Tourism topics
|
On-track to meet
all goals and objectives for this month and end of year.
|
| May
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "dynamic" Space Tourism topics
|
On-track to meet
all goals and objectives for this month and end of year.
|
| June
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "dynamic" Space Tourism topics
complete
- Release upgrades
to Universal Space Systems Web site as needed
- Assess second quarter's performance
|
On-track to meet
all goals and objectives for this month and end of year.
|
| July
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "static" Space Tourism topics
- Planned
completion of one-third of the contents for
the Space Adventurer
Assessment/Report
|
On-track to meet
all goals and objectives for this month and end of year.
|
| August
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "static" Space Tourism topics
|
On-track to meet
all goals and objectives for this month and end of year.
|
| September
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "static" Space Tourism topics
- Planned
completion of two-thirds of the contents for
the Space Adventurer
Assessment/Report
- Release upgrades
to Universal Space Systems Web site as needed
- Assess third quarter's performance
|
Although
we are slightly behind in content completion for the SAAR at this point in
time, we will be back on track by next month. |
| October
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Continue documenting research and data for the Space Adventurer
Assessment/Report - focus on "static" Space Tourism topics
|
On-track to meet
all goals and objectives for this month and end of year.
|
| November
Planned Activity
- Continue research, data gathering and analysis for
the Space Adventurer
Assessment/Report
- Complete documenting research and data for the Space Adventurer
Assessment/Report - focus on "static" Space Tourism topics
|
|
| December
Planned Activity
- Finalize documenting research and data for the
first release of the Space Adventurer
Assessment/Report
- Evaluate release of
“satellite” Web sites and Client Web page
- Release upgrades
to Universal Space Systems Web site as needed
- Assess fourth quarter's performance
|
|
For our third year of operations, we have achieved all
of our goals and objectives after again making readjustments in the 4th quarter to delay the 1st release of the
SAAR. This delay is based on new operational launch dates being revised by key sub-orbital Space Tourism
Companies with a projected 1st commercial sub-orbital spaceflight to occur NET
2010:
In the second year of operations Universal Space Systems has achieved all
of its goals and objectives after making readjustments in the 3rd quarter to delay the 1st release of the
SAAR based on new operational launch dates being revised for key sub-orbital Space Tourism Companies:
In the first year of operations Universal Space Systems has achieved all
of its goals and objectives: